The Roosevelt City Street Reconstruction Project is moving forward quite well. The Contractor is installing the culinary water meters and repositioning them behind the sidewalks on 100 West. They have finished installing secondary water on 100 West and 100 North. In approximately 2 weeks installation of culinary and secondary lines will begin on 100 South and 400 East. As a reminder, the streets will be repaved after the installation of culinary and secondary lines is completed. 100 W Street in Roosevelt After Excavation and Repositioning of Water Meters
100 N Street in Roosevelt After Water Line Installation